11/13/2018 East Rec Progress

Last Updated: 11-13-18

The concrete foundation for the small two story addition has been poured and the retaining walls. Lumber for framing arrives tomorrow and framing for the addition begins this week.


Below is the forming in the newly dug hole for the new spa/hot tub.


Now that all of the soil has been carefully compacted around the pool, the trenching for the new pipes and wiring is being completed , as you can see below.


New Piping is being restored and relocated has begun. (The old pipes ran exactly where the piers for the new deck are to be located.)


As a reminder of the new upstairs bathroom tile layouts, here is the timeless white subway tile pattern artfully drawn by Kasten and Harris.

The plumbers have done the rough in for the new locations of the toilets.
The grid work for the acoustic tile ceiling is being installed.
The Audio visual contractor started running wiring today at 7 am for the new “au current” audio visual system being installed.
David and I met the HVAC specialist to confer about the final details of the downstairs baths’ ventilation.

Berger seismic work scheduled for the beginning of December.

Onward!

Iris F. Harrell
OVA Chair of the BCC

We are all in this together…2018